Update on the R511/M26 Road

r511

I’ve received many queries about the R511/M26 road between Erasmia and Diepsloot. The contractor abandoned the work last year after digging up about 4km of the tarmac. Road conditions are very poor.

Here is a update from Gauteng Roads and Transport MEC, Ismail Vadi:

Dear Yusuf, 

The factual position is as follows:

The Department terminated the contract due to poor/unsatisfactory performance of the contractor. 

On this score, it acted in the public interest.  

The Department has extended the scope of work (for further improvements on the road), which has additional budgetary implications.

An application has been made to Provincial Treasury for additional funding and the Department is awaiting a decision from Treasury.

The Department cannot proceed with the revised tender until there is authorisation from Treasury. This is a legal requirement.   

I hope this clarifies the matter.

1 comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

  • What can we do about the safety on the m26 road. The damages that happen to the cars. What about the medical problems for the people on the side of the road. Motorbike suffer. Entrances dangerous loos gravel.

Previous post Madiba: Let’s Show Some Respect
Next post National Orders 2013 on SABC 2
image/svg+xml

Menu

Follow me

Recent Posts

Recent Comments

Archives

Categories